Ramgarh Gas Thermal Power Station
Ramgarh gas thermal power station is the first gas thermal power plant of Rajaisthan. The first unit was commissioned on dated 15-11-1994. |
LOCATION
Ramgarh gas thermal power plant station is situated near village Ramgarh, 60 kms away from Jaisalmer. The first unit of 3 MW is not in operation now. The present installed capacity of the plant is 270.50 MW.
|
|
Stage
|
Unit No.
|
Capacity (MW)
|
Cost (Rs. Crore)
|
Synchronising Date
|
I
|
Gas Turbine # 1
|
35.5
|
180
|
12.01.1996
|
II
|
Gas Turbine # 2
|
Unit No.
|
300
|
07.08.2002
|
Steam Turbine, STG # 1
|
37.5
|
25.04.2003
|
III
|
Gas Turbine # 3
|
110
|
640
|
20.03.2013
|
Steam Turbine, STG # 2
|
50
|
01.05.2014
|
|
|
Operational Performance of Plant
|
Particulars
|
2006-07
|
2007-08
|
2008-09
|
2009-10
|
2010-11
|
2011-12
|
2012-13
|
2013-14
|
2014-15
|
2015-16 |
2016-17 |
2017-18(Upto Nov17) |
2017-18(UptoDec17) |
2018-19(March2019) |
Gross Generation (LU)
|
4041.440
|
4141.153
|
3486.782
|
3539.44
|
3028.85
|
5367.94
|
4979.06
|
6733.195
|
1260.69(MU)
|
1522.57(MU)
|
138.81(MU)
|
1006.95(MU)
|
1115.60(MU)
|
998.06
|
Plant Load Factor (%)
|
41.75%
|
42.78%
|
36.00%
|
36.57%
|
31.29%
|
55.30%
|
51.44%
|
52.92%
|
55.41%
|
64.08%
|
68.97%
|
63.57%
|
62.49
|
42.12
|
Aux.Consumption(%)
|
-
|
-
|
-
|
7.88
|
5.30
|
1.78
|
1.48
|
3.29
|
4.30
|
4.15
|
3.93
|
3.97
|
3.98
|
4.26
|
Gas Consumption(SCM/kwh) |
- |
- |
- |
0.64 |
0.61 |
0.55 |
0.55 |
0.59 |
0.38 |
0.34 |
0.35 |
0.34 |
0.34 |
0.413 |
SHR(Kcal/kwah) |
- |
- |
- |
2514 |
2693 |
2587 |
2572 |
3203 |
2577 |
2393 |
2172.33 |
2292.61 |
2285.51 |
2465.99 |
Availablity (%) |
- |
- |
- |
61.66 |
54.99 |
86.23 |
69.79 |
83.76 |
78.02 |
79.54 |
96.77 |
77.41 |
76.90 |
68.54 |
|
|
EXPANSION
|
GAS THERMAL POWER PROJECT- STAGE III
The Gas Unit of 110 MW commissioned on 20.03.2013 and the Steam Unit of 50 MW has been synchronized on dated 05.04.2014. At present activities for the COD of the 50 MW STG unit is under way.
|
STAGE-III (Salient Features)
|
1.
|
Capacity
|
160MW
|
2.
|
Location
|
Ramgarh
|
3.
|
Total plant area
|
796 bigha,17 biswa
|
4.
|
Project cost
|
640 crores
|
5.
|
Fuel
|
GAS and HSD
|
6.
|
Source of water
|
Indra Gandhi canal
|
7.
|
Fuel required
|
9.5 lac. SCM per day
|
8
|
Water allocation
|
10.8 cusecs
|
|
|
|